February Core Metrics

published by Rob Blair

Want to create a visual like this?

Get Started
Loading
Core Services Metrics
February
Mantis Separation: Reads
February deliverables
Mantis - Offline PCS Integration
In Progress [completed/to do]
HCore Hcom Modules Upgrade [2/3]
LDS V3 Upgrade work [3/4]
Mantis Separation: Delete/Update [1/6]
Mantis Separation: Writes [12/13]
PCS Filter By Pimms [7/9]
HCore Pipeline [4/7]
HCore Improve the Monitoring and Alerting Tooling [3/9]
SRP Geo Bullets Via PCS
[CES 1.2] Happy Path Stage 2 [2/4]
[CES 1.2] Happy Path Stage 1 [1/3]
PPS AvailDetail Via LPAS
Upgrade to TFN service
Core Key Metrics For February
HCore Historical Cycletime
HCore Team Index
HCore Bugs in February
Number of bugs created: 13
Number of bugs resolved: 12
Bug count at month end: 1
11 Developers
18 Bugs fixed
23 Items delivered
Average Cycle time is 7d 19h
HCore Summary
Number of stories: 10
Cycle time: 4.29
No. of bugs fixed: 8
Number of tech debt items: 10
Team Happiness: 7
HCore Historical Throughput
HInt Summary
Number of stories: 13
Cycle time: 10d 12h
No. of bugs fixed: 10
Number of tech debt items: 1
Team Happiness: 8.8
HInt Historical Throughput
HInt Historical Cycletime
HInt Team Index
HInt Bugs in February
Number of bugs created: 9
Number of bugs resolved: 15
Bug count at month end: 2